Wednesday, November 18, 2026

Australia's Grandfathered Giants: 27 AI Data Centres Poised to Sidestep Federal Water and Power Standards - Lethal Heating Editor BDA

Twenty-seven approved AI data centres could escape Australia's
incoming water and renewable energy rules
Key Points
  • The ABC found 27 approved but unbuilt data centres totalling at least 3.38 gigawatts. Australia's 162 existing facilities hold roughly 1.5 gigawatts.[1]
  • The Prime Minister says the 2027 standards will skip approved projects. A September consultation paper reopens that question.[2]
  • NSW has asked IPART to design water pricing that makes operators fund their servicing costs.[3]
  • Sydney Water says data centre water demand could reach 250 megalitres daily by 2035.[4]
  • Climate Council modelling links gas-backed growth to wholesale price rises of up to 26 per cent in NSW.[5]
  • AEMO expects data centres to use 34 terawatt-hours by 2035-36, about 13 per cent of grid supply.[6]

Jack Tollefsen tends a community garden on Sydney's western fringe and works down the road from NEXTDC's S4 data centre. 

The Horsley Park facility, under construction, will supply 365 megawatts of capacity. 

Tollefsen has started a petition, because Prime Minister Anthony Albanese says the 2027 federal standards will skip projects like it.[1]

An ABC analysis found 27 approved but unbuilt data centres totalling at least 3.38 gigawatts. 

One gigawatt equals 1,000 megawatts, and Australia's 162 existing facilities hold roughly 1.5 gigawatts of IT capacity.[1]

The 3.38-Gigawatt Exemption

Albanese announced national AI and data centre standards in July, with legislation due in early 2027. 

He later told ABC Radio Sydney that retrofitting is impossible and that many projects under construction run smaller.[1]

A September consultation paper from the Department of the Prime Minister and Cabinet reopens the question. It asks whether standards should reach projects still unfinished when the law starts. Centres below 30 megawatts could escape entirely, while larger facilities would face tougher tiers.[2]

Large facilities would bring forward new renewable generation to offset their demand and adjust load to support the grid. Water rules would require recycled or non-drinking supplies, drought preparation and public reporting of use. Grandfathering, the practice of letting earlier approvals keep their old terms, would spare the 27 projects each obligation.[2]

The Climate Council rejects the retrofit argument. Its open letter urges the Albanese Government to make the rules retrospective, so they apply to every new data centre. The council says the government should close those gaps before the standards take effect.[7]

Mapping the Exempt Pipeline

RenewMap analysts say the pipeline concentrates in Western Sydney and on Melbourne's outskirts. The ABC's list covers projects from Amazon Web Services, Microsoft, AirTrunk, CDC and NEXTDC, plus property groups Goodman and Stockland.[1]

Goodman's five-storey Project Apollo in Sydney's north gained approval in early September, with NSW conditions on water and energy use. Federal rules will skip it. RenewMap's Alex Thompson warns that some approved projects will stay unbuilt.[1]

Victoria's Premier, Ben Carroll, announced his own data centre rules on 22 September. New facilities would need their own renewable supply, and Carroll wants zero drinking water used for cooling. The rules carry no retrospective reach for applications under assessment, so approved projects sit even further outside them.[8]

State governments retain planning responsibility, so approval conditions such as those on Project Apollo set the enforceable limits for now. Greens senator Sarah Hanson-Young says rules that skip approved projects are worthless without a moratorium on new approvals.[1]

The Draw on Drinking Water

Evaporative cooling removes heat by evaporating water in cooling towers, and the water never returns. Operators report efficiency as water usage effectiveness, or litres per kilowatt-hour of computing energy. A megalitre equals one million litres and a gigalitre one billion.[4]

Published benchmarks span a wide range, and closed-loop cooling, which recirculates water, sits at the low end. CDC reports 0.01 litres per kilowatt-hour, AirTrunk reported 0.97 for the 2024 financial year and NEXTDC reported 2.25 for 2025.[9]

Illustrative arithmetic treats 3.38 gigawatts as computing load running at half capacity, or 14.8 terawatt-hours a year. AirTrunk's benchmark implies about 14 gigalitres a year, or 39 megalitres a day. NEXTDC's benchmark implies about 33 gigalitres, or 91 megalitres a day.

Those results run from 2.6 to 6 times the 5.5 gigalitres that industry analysis attributes to the whole sector today. Sydney Water told a NSW inquiry that cumulative demand could reach 250 megalitres daily by 2035. Single applications ask for up to 40 megalitres daily, though that figure marks a maximum connection rather than expected use.[4]

Grid Strain and Power Prices

AEMO forecasts that grid data centre use will climb from 5 terawatt-hours in 2025-26 to 34 by 2035-36. That lifts their share of National Electricity Market supply from around 3 per cent to about 13 per cent. A terawatt-hour equals one billion kilowatt-hours.[6]

The Climate Council warns against matching data centre growth with gas rather than renewables. Wholesale prices could rise by up to 26 per cent in NSW and 23 per cent in Victoria by 2035. Without intervention, it says, demand would delay coal retirements and deepen reliance on gas.[5]

In NSW, data centres sought connections totalling up to 28 gigawatts as of July, with 13 gigawatts in advanced talks. The state's paper proposes a default Major Network Upgrade Fee of $200,000 per megawatt of capacity.[10]

Federal standards would require large centres to minimise costs for households and businesses. Exempt projects fall outside that test, so state connection fees and network regulators decide who pays.[2]

Transparency and Accountability

The Water Services Association of Australia urges developers to engage early and publicly report each facility's water and energy use. Exempt projects face no federal reporting duty, so communities depend on state conditions and voluntary disclosure. Public figures would let residents test developers' water claims against actual use.[4]

The NSW Government has asked IPART to recommend a water pricing and regulatory framework for data centres. The brief says operators should fund the upfront and ongoing costs of servicing them, without burdening existing customers.[3]

Pricing attaches to water connections rather than planning consent. Approved projects still awaiting a connection could therefore face new charges even though their approvals stand. The review has yet to report on that question.[3]

Journalists and residents hold one lever today. Applications under NSW's Government Information (Public Access) Act 2009 can seek records from state agencies and water utilities. Victoria's Freedom of Information Act 1982 offers a similar route for Melbourne's projects.

The 3.38-gigawatt pipeline shows how timing can decide who carries the cost of Australia's AI boom. The Prime Minister says retrofitting is impossible, yet the consultation paper keeps the question open for the 27 approved projects.

Water and power arithmetic points to real exposure for Sydney and Melbourne catchments and networks. Published figures leave each approved site's drinking water allocation unclear, which weakens public scrutiny.

Accountability now depends on the final 2027 law, IPART's pricing review and state approval conditions. Governments can close the gap by requiring metering, public reporting and recycled supply at every approved project. Residents in growth corridors need that clarity before the first cooling tower starts.

References

1. The bigger, hungrier AI data centres set to escape looming water and power restrictions. ABC News, 11 September 2026. Analysis that identified 27 approved but unbuilt data centres totalling at least 3.38 gigawatts.

2. AI companies would need to report 'rogue' incidents under proposed national standards. ABC News, 18 September 2026. Summarises the consultation paper's energy and water proposals and its question on pipeline projects.

3. Review of the water pricing framework for data centres. IPART, 2026. Sets out the NSW Government reference asking operators to fund the costs of water servicing.

4. What AI data centres really mean for Australia's water supply. University of Melbourne Pursuit, 3 August 2026. Explains evaporative cooling, sector water use and Sydney Water's 250 megalitre warning.

5. Clouded Future: Managing the risks of the data centre boom. Climate Council. Models wholesale price risks and reports single-site water connection requests of up to 40 million litres daily.

6. 2026 ESOO Data Centre Forecasting Overview. AEMO, 2026. Explains how the market operator forecasts data centre demand through to 2035-36.

7. Data Centres Open Letter. Climate Council, September 2026. Calls on the Albanese Government to make data centre rules retrospective.

8. We Need Data Centres But We Set The Rules. Premier of Victoria, 22 September 2026. Announces Victoria's proposed rules and confirms they carry no retrospective reach.

9. Australia's data centre water debate needs to cool down. Overnight Success. Compiles water usage effectiveness figures from CDC, AirTrunk and NEXTDC sustainability reports.

10. Hefty network fees discussed as state government reveals massive scale of data centre grid connection demands. RenewEconomy. Reports NSW connection requests of 28 gigawatts and a proposed $200,000 per megawatt network upgrade fee.